Project Quick Facts

- Location: Sirsiya, Nepal
- Delivery Year: 2024
- Site Scale: Approx. 10,000 sqm (1 Hectare)
- Project Scope: Full turnkey masterplan + 14 sets of amusement rides
- Client Goal: Build the premier regional family entertainment center within a 6-month timeframe.
Core Equipment Matrix & Parameters
To maximize the 10,000 sqm footprint, we supplied a diverse 14-ride matrix tailored for all age groups. Key attractions include:
- Self-Control Plane: 16-24 capacity | 14m diameter (Family interactive focus)
- Classic Carousel: 36 seats | 10m diameter | 7.5kW (Visual centerpiece)
- Pirate Ship: 24 seats | ±45° swing angle (Mid-level thrill)
- Wacky Worm Coaster: 120m track length | 14-person train (Parent-child friendly)
- Elevated Bike: 3.5m-5m track height | Manual + Motor assist (Scenic perimeter ride)
- Flying Chair: 12m rotating diameter | 24 seats
- Auxiliary Rides: Floor-Grid Bumper Cars, Flying Car, Commercial Inflatable Castle, etc.
▶ Watch in Action: 24-Seat Flying Chair (Smooth Operation & Night Visuals
▶ Watch in Action: 120m Wacky Worm Coaster (Track Stability & Family Fun
Key Challenges & LIMEIQI’s Turnkey Solutions
Challenge 1: Extreme Cross-Border Logistics to a Landlocked Region
- The Hurdle: Nepal is a landlocked, mountainous country. All 14 sets of equipment had to be shipped to a transit port in a neighboring country (like India) before undergoing a prolonged, highly bumpy overland truck journey. The massive steel tracks of the Wacky Worm Coaster and the heavy pendulum arms of the Pirate Ship were at high risk of structural deformation or paint abrasion during this transit.
- Our Engineering Solution: LIMEIQI’s export department executed a pre-calculated 3D container loading simulation to maximize space utilization, directly saving the client thousands of dollars in freight costs. For the overland journey, all critical mechanical joints and FRP (Fiberglass Reinforced Plastic) cabins were secured using heavy-duty, shock-absorbing wooden crating and multi-layer anti-corrosion wrapping. The equipment arrived in Sirsiya in pristine, factory-new condition.
Challenge 2: Precision Foundation Pouring & Localized Installation
- The Hurdle: As first-time investors, the Sirsiya developers lacked experience in specialized civil engineering. High-dynamic-load rides, such as the ±45° swinging Pirate Ship and the rotating Flying Chair, require millimeter-precise reinforced concrete foundations. A slight deviation in anchor bolt placement could lead to severe operational vibrations and safety hazards.
- Our Engineering Solution: Weeks before the equipment arrived, we provided the client with fully translated, standardized foundation blueprints. Once the concrete was cured, LIMEIQI dispatched our senior technical team to Nepal. Our engineers personally supervised the secondary grouting, track splicing, and structural welding. We transformed an inexperienced local construction crew into a capable installation team through on-site, hands-on guidance.
Challenge 3: Zonal Planning & Electrical Adaptation in a 10,000 sqm Site
- The Hurdle: Operating 14 major attractions simultaneously in a 10,000 sqm park requires not only flawless crowd flow management to prevent bottlenecks but also a highly stable electrical control system capable of handling local voltage fluctuations.
- Our Engineering Solution: Spatially, we adopted a revenue-driven layout. We placed high-throughput “traffic absorbers” like the 36-seat Carousel near the entrance, and utilized the 200m Elevated Bike track as a dynamic perimeter boundary, freeing up valuable central space for the Self-Control Plane and Bumper Car family hubs. Electrically, our factory customized all ride control cabinets with voltage-stabilizing components to adapt seamlessly to the local South Asian power grid, ensuring uninterrupted daily operations.


💡 Every investment site has its own unique geographical constraints and logistical hurdles. Overcoming these complex engineering challenges is the core of our turnkey service. See how our systematic approach protects your investment from factory to grand opening.
Why the Client Chose LIMEIQI (The Source Manufacturer Advantage)
For a first-time investor, mitigating risk is just as important as the equipment price. The Sirsiya developers bypassed trading companies and chose LIMEIQI for three critical reasons:
- Authentic Manufacturing Legacy: With 40 years of direct manufacturing experience, we eliminated all middleman markups, allowing the client to allocate their saved budget toward better park landscaping and marketing.
- Uncompromising Safety Standard: The amusement industry leaves no room for error. LIMEIQI proudly maintains a 40-year zero safety accident record, ensuring that every weld, motor, and track joint meets the highest international operational standards.
- Global Delivery Capability: We brought extensive export and localized service experience spanning over 120 countries. This expertise guaranteed the client seamless customs clearance, specialized overland routing to Nepal, and culturally adapted operational training for their local staff.
Final Outcome & ROI Data
- On-Time Delivery: The 10,000 sqm park transitioned from a vacant lot to fully operational right on schedule for the 2024 peak tourism season.
- Revenue Performance: High-capacity rides like the Carousel and Self-Control Plane successfully handled massive holiday crowds.
- Projected ROI: Based on current ticket turnover, the park is on track to achieve a full return on investment within 12 to 15 months.



Project Experience & Next Steps
The successful delivery of the Sirsiya project proves that building a highly profitable 10,000 sqm park in an emerging market requires more than just purchasing rides. It demands a manufacturer capable of unified site planning, rigorous safety engineering, and robust cross-border execution.
Ready to turn your vacant land into a highly profitable family destination? Stop guessing the layout and budget. Send us your site dimensions today, and our factory team will provide a customized, high-ROI ride mix plan and a direct manufacturing quote.